Hey Guys/Gals, I am looking into installing a high-temperature oven that uses 12 heating rods, the rods are wired WYE, 277V, 62 amps each, the manufacturer recommends 350°C wire for the termination. The feed wires come from 4 power regulators and are about 30-40 feet away. 
My question
Can I run a TECK cable to a junction box and feed the oven from there, if so what would be the minimum length of high-temperature wire from the JB to the oven. I can't seem to find anything concrete in the CEC
Thanks for any input