Is there a limit to the number of circuits that can be in a single conduit (Beyond standard installation requirements)? Will 2-3 circuits per homerun affect the isolation panel / ground testing? Should each circuit have a dedicated homerun? My questions are based on a situation where a headwall is served by multiple isolated power circuits; can these be combined without having future problem when the system is tested?
Any information would be appreciated.