hhsting
Senior Member
- Location
- Glen bunie, md, us
- Occupation
- Junior plan reviewer
Building is existing and owner says no to povide new utility service thru underground. You can see post #3 Figure #1 two utility service into one building. To eliminate one utility service bring service disconnect of tenant A to basement trough and feed tenant A panelboard.I simply don't understand why the service conductors don't go into a gutter at or near the closest point of entry to the structure, and, the (2) service disconnects tapped at that point.
That wouldn't be my first choice of distribution, but, just going off what is drawn.
I don't see the need for a Main OCPD then the feeders being Sub-Metered.
If you only have (2) Service disconnects to feed, why aren't the service entrance conductors simply brought into a gutter at or near the closest point of entry, and, the (2) Service disconnects metered separately at that point without the Main OCPD ?
JAP>
Sent from my SM-G935U using Tapatalk