How long will it take?

Status
Not open for further replies.

220wire

Member
without going into I have a 5300sqft office buildingwith a 600a service- 2 200apanels near mdp, elevator 30' away, aprox 50 luminaires with occ.sensors(whatever the hell those are), and 50 general purpose receps, fire alarm- 20 devices.

conduit for home runs, mc for branch wiring

I am guesstamating 6-8 weeks.
Am i off?
 

cowboyjwc

Moderator
Staff member
Location
Simi Valley, CA
occupancy sensors. If you're talking total job you may be right, but sounds a little long for just electrical. But I've been out of it for awhile too.:grin:
 

chris kennedy

Senior Member
Location
Miami Fla.
Occupation
60 yr old tool twisting electrician
without going into

Well your going to have to if you want a estimate from us. Floor boxes, power poles, modular furniture or heaven forbid a designer involved?

I am guesstamating 6-8 weeks.
Am i off?
Your on the conservative side IMO. But this of coarse depends on the GC and other subs, do you know these guys?

Also, if you can get away with it, put in your proposal that the OS's are supplied by others and will be installed at default settings. This will save you call backs and headaches.
 