Not exactly a high rise, the job I'm running now has four stories of stick framed residential units, which will be wired with Romex. AHJ will not allow us to run wire until it is roofed and windows are in, giving us 5 months from the beginning of rough in to CO on 115 units with 277 beds and baths, full kitchens in each, and about 1500 fire alarm devices. I agree with you, just wish my inspector felt the same...
Maybe plastic or plywood over the window openings would make him happy.
I think he's wrong, but if you can't convince him otherwise, maybe a temporary barrier will suffice.