Alwayslearningelec
Senior Member
- Location
- NJ
- Occupation
- Estimator
Guy I really need help with this as I beleive it's been skewing my prices. INterior renovation work only.
As I've stated before the two main things that are based on schedule/ job duration.
For instance today I bid a interior renovation job in which I had 2,500 direct labor install hours.
It was a commercial renovation. 8,000 sq ft.
The specs called for the job to be 28 month durations.
So I figured a PM for about 2-3 hours a week average for the 28 months.
Also, figured my working foreman would not be working about 2 hours a day so I figured 2 hours a day for the 28 months.
The owner went along with it.
I don't think that is the right approach.
Shouldn't I some way try to figure out how ling we will be needed on the job???
Just because there is a given project schedule does not mean the electrical will be onsite that entire time, correct?
Thanks
As I've stated before the two main things that are based on schedule/ job duration.
- PM
- Foreman Non working time
For instance today I bid a interior renovation job in which I had 2,500 direct labor install hours.
It was a commercial renovation. 8,000 sq ft.
The specs called for the job to be 28 month durations.
So I figured a PM for about 2-3 hours a week average for the 28 months.
Also, figured my working foreman would not be working about 2 hours a day so I figured 2 hours a day for the 28 months.
The owner went along with it.
I don't think that is the right approach.
Shouldn't I some way try to figure out how ling we will be needed on the job???
Just because there is a given project schedule does not mean the electrical will be onsite that entire time, correct?
Thanks