so, a 25' #4 copper wire was used to connect the rebars with a 8' copper rod, which was driven into the ground (1), and the town inspector came out and had us placed a J rebar with wire ties on the footer (3), and then sticking a short #4 rebar into the ground and connect it to the J rebar (2).
Then he approved the slab and footer.
I am not aware that this is a code-compliant method.
Does anyone has an insight to this?
so, a 25' #4 copper wire was used to connect the rebars with a 8' copper rod, which was driven into the ground (1), and the town inspector came out and had us placed a J rebar with wire ties on the footer (3), and then sticking a short #4 rebar into the ground and connect it to the J rebar (2).
Then he approved the slab and footer.
I am not aware that this is a code-compliant method.
Does anyone has an insight to this?