I am specifying a project (I am not an electrician) and inquiry how to surface mount up to 8 L6-30Rs on a plywood wall. These will be servicing PDUs in racks.
The servicing panel is on the same wall about 5 feet away. I cannot use a distribution system in the racks as the racks and PDUs may be changed out in the future, thus using PDUs with 10' whips from the racks to the wall using ladder or cable tray to manage the whip cables.
Is there a work box or enclosure that can accommodate multiple L6-30Rs or would I need a separate 4X4 work box for each outlet?
The servicing panel is on the same wall about 5 feet away. I cannot use a distribution system in the racks as the racks and PDUs may be changed out in the future, thus using PDUs with 10' whips from the racks to the wall using ladder or cable tray to manage the whip cables.
Is there a work box or enclosure that can accommodate multiple L6-30Rs or would I need a separate 4X4 work box for each outlet?