We're installing an auto transfer switch ahead of an existing main service panel. The 2 feeds will be from separate padmounted transformers on different distribution systems. The neutral conductors would normally be grounded in the transformers. The plan is to install service entrance disconnects between each transformer and the ATS. It seems the neutrals should be grounded and bonded in each new service disconnect (correct?) but would there need to be changes made in the existing service panel too?