My work has been all resi NM to date and I'm starting to do some EMT work. I recognize the install learning curve is on me. My question is about pricing. I've seen info on this form and others quoting labor at 4-8 hours per 100ft of 3/4 EMT installed, pulling 3-10AWG stranded 2-6 hours per 100ft, with the range covering degree of difficulty, number of boxes, etc.
My next job is in the 50x60 garage of a barndo, 32ft center height. I'll be installing high bay lights and general use 20A receptacles around the perimeter. Are folks pricing generally per foot EMT, per foot wire pulling? and how much?