triplstep
Member
- Location
- Aurora, Illinois
I went to install a swag lamp on a ceiling today in a small commercial building. A receptacle was to be mounted flush with the ceiling to energize the lamp using the switch. The ceiling had existing layins, connected with fmc, fed from one jb. Two 1/2 emt were also connected at the jb, one with three conductors, no white or gray, and the other a white and black.
Of the three conductors in one raceway, two were ungrounded, and black was used as the grounded, 120 volts. The raceway with the black and white conductors were used as the switch leg. The white was used as the return leg.
I told the customer I did not want to complete the installation with the current violations. I did tell them I'd correct them, and said that probably I could complete it in a days work or less. They asked if it was a fire hazard, no, but making connections to a violation is not my thing. As the tenant, they did not want to sign off on that. I replaced the ceiling tile and headed out of dodge.
What would you have done?
Of the three conductors in one raceway, two were ungrounded, and black was used as the grounded, 120 volts. The raceway with the black and white conductors were used as the switch leg. The white was used as the return leg.
I told the customer I did not want to complete the installation with the current violations. I did tell them I'd correct them, and said that probably I could complete it in a days work or less. They asked if it was a fire hazard, no, but making connections to a violation is not my thing. As the tenant, they did not want to sign off on that. I replaced the ceiling tile and headed out of dodge.
What would you have done?