I am doing a high-rise condo project and the gas goes to all 89 units. There is one gas service with a manifold type set up for the meters. All of the stubs for the gas are at the manifold. The gas company told me not to bond the pipe at the main. I have all these stubs to bond. Do you think it would be acceptable to bond the first one and rely on the unistrut rack as continuity for the rest? Or do I have to bond every one of them?