I pulled a permit for recently installed portable generator for my home with an interlock. I placed an 30A double-pole breaker to backfeed from generator to the panel. The interlock was screwed to the cover of the panel to prevent turning on the main breaker while generator is running. When the inspector came to inspect the work, he wanted me to put the circuits in a subpanel for the generator because the 30a generator is not sufficient to power the whole panel. I explained to him I am not intended to power the whole house and will only power what I need for that time.
Does anybody know if this is a code violation? The interlock is UL listed. If I separate out the circuits in sub panel that means I have to use transfer switch. Thanks for any advice you can provide.