The installation is EMT sleeves under a basement ceiling laminate beam for physical protection of Romex that's just passing thru.
I'm looking at 250.132, 300.12x1, + 334.15(C).
300.12x1 says that not having mechanical continuity is OK
but 250.132 + 334.15(C) seem to say that bonding is still an issue
Anybody have a thought or 2.
I'm looking at 250.132, 300.12x1, + 334.15(C).
300.12x1 says that not having mechanical continuity is OK
but 250.132 + 334.15(C) seem to say that bonding is still an issue
Anybody have a thought or 2.