Junction Box or Tapping box - city of chicago

Status
Not open for further replies.

inforaj

Member
Location
Chiago
Occupation
Member
Hi Everyone,

I wanted to know before submitting the plan that the city of Chicago will require 3 to 6 months for permits. Will the city of Chicago permit the tapping/junction box, or won't they? My friends said they wouldn't permit it, but he's unsure.


Thank you in Advanced.
 

ggunn

PE (Electrical), NABCEP certified
Location
Austin, TX, USA
Occupation
Consulting Electrical Engineer - Photovoltaic Systems
Sorry for the confusion. Solar back feeding tapping box or junction box with Insulation Piercing tap connectors at point of interconnections.
Assuming that you are speaking of a supply side connection, someone at the AHJ should be able to tell you if they are enforcing 230.46 or if they are invoking 90.4 to delay enforcement until compliant hardware is available. We are dealing with AHJs on both sides of that fence.
 