Don’t know why but I just read this entire thread. This thread sounds to me like someone who is hunting for a reason to not pay their bill by saying he done this or he done that. :rant:
I don't know what the total cost of this project is, but it easily exceeds $1M. I also don't know how much the contractor is getting paid, but I do know it's a LOT of money. I also know that the contractor has been receiving (large) payments in installments on a scheduled basis per his contract. No monies have been withheld.
We are not -- in any way, shape, or form -- trying to avoid paying our bills. In fact, the owner has been
more than fair with this contractor.
This is a large solar array project and it qualifies for a federal rebate equaling 30% of all expenses (materials and labor). The job was supposed to be completed, per contract, by mid-September so the owner could get the rebate paperwork filed by a 30 September deadline. The job is not yet completed, and will not be complete for at least another week. Not only are we losing revenues on the power we should already be producing, but because the contractor caused us to miss the initial rebate filing deadline, our rebate application will have to go through a slower and more rigorous approval process.
There were performance milestones written into the contract with the electrical contractor; there were financial penalties for missing those milestones. At the beginning of the job, the contractor made a big mistake: he erroneously ordered all the fasteners and strut for the array framework in electrogalvanized (EG) finish, even though stainless steel and hot-dipped galvanized were clearly specified in the engineered plans. Despite being told he had the wrong materials, he was in such a hurry to get started that, instead of waiting for the correct parts to arrive, he proceeded to frame two of our arrays with the EG parts. At that point, the owner realized that the contractor was going to sacrifice quality in order to meet the performance milestones, so we removed those penalties from the contract.
After that, the contractor was so laid-back about the project that he wouldn't even show up to the job site for days on end. One of the milestones was to have our service-entrance switchgear installed, and the feeders pulled (the subject of this thread), by the end of August. The feeder pulls did not begin until September 8, and were not completed until September 27. The switchgear didn't even arrive on site until September 21. We recently learned that the reason the switchgear was delayed by over a month was because the contractor was holding off on the order to try to negotiate a lower price for himself from the manufacturer.
Did I mention that the contractor took a personal vacation from September 11 to September 19, and did not return to the job site until September 21?
Has anyone counted how many times someone has made the statement that these practices are done all the time in this thread? I know that I read it more than once. How many times and by how many different people does this need to be said? :happysad:
I read them and accepted those opinions. I also read the opinions of those people who agreed I had some legitimate concerns. I continue to welcome opinions supporting either position.