billdozier
Senior Member
- Location
- gulf coast
Diferent job today had some highbay lights from original warehouse which had been refurbished to church. Acoustical cieling had been installed but fire marshall wanted to add fire wall. So we were asked to pull plugs out of existing wall and installed in fire wall. My question is these highbays which have done nothing to do with our bid. By code should they not have been deleted as well as pipe feeding them? If you were an inspector would you make us demo these conduit runs and lights?