Chris Lovingood
New member
- Location
- San Diego
Hello all,
I have question in regards to load calculations. A customer wants to add a 1ea-125A and 1ea-225A circuit breakers on a existing 400amp panel that already has (3ea) 200amp circuit breakers.
The reason the customer wants to add the two circuit breakers to the 400amp is that they are on a back-up generator.
This 400amp power panel powers a computer lab with multiple computer servers. The transformer is rated 75kVA, 480volts primary & 120/208Y secondary.
My Questions:
I figured the best option is to do amperage reading throughout the business day since we do not have a amp recording meter. Is this the best way to do this?
Also, is the 75kVA transformer undersized? I did the calculations and its telling me I need a least a 112.5kVA transformer.
Any help, advice, & experience would be much apprieciated. Thank you.
v/r,
Chris
I have question in regards to load calculations. A customer wants to add a 1ea-125A and 1ea-225A circuit breakers on a existing 400amp panel that already has (3ea) 200amp circuit breakers.
The reason the customer wants to add the two circuit breakers to the 400amp is that they are on a back-up generator.
This 400amp power panel powers a computer lab with multiple computer servers. The transformer is rated 75kVA, 480volts primary & 120/208Y secondary.
My Questions:
I figured the best option is to do amperage reading throughout the business day since we do not have a amp recording meter. Is this the best way to do this?
Also, is the 75kVA transformer undersized? I did the calculations and its telling me I need a least a 112.5kVA transformer.
Any help, advice, & experience would be much apprieciated. Thank you.
v/r,
Chris