Is it typical to implement a M-T-M transfer scheme on a LV or MV switchgear lineup with only PT's on line side of breaker (No Bus PT's). Are bus PT's typically only required if a closed transition scheme is being implemented? If only an open transition scheme is implemented are only line side PT's required with necessary breaker interlocking.
The application I'm referring to here is relay based transfer schemes implemented with relay control.
The application I'm referring to here is relay based transfer schemes implemented with relay control.