Jerry Chernich
New member
I am currently working on a commercial project tat has this requirement in its specifications. The water pipe gound is to be supplemented by an additional made electrode consisting of ground rods laid on 3 inch 75mm charcoal bed.
The water main is bonded the buiding steel is bonded and the rebar in the foundation is bonded. Other than the specs saying it has to be done what purpose does this serve? I've been in the trade 28years and this is new to me. Anybody ever encounter this and if so could you furnish some details.
Thanks J Chernich
The water main is bonded the buiding steel is bonded and the rebar in the foundation is bonded. Other than the specs saying it has to be done what purpose does this serve? I've been in the trade 28years and this is new to me. Anybody ever encounter this and if so could you furnish some details.
Thanks J Chernich