Just installed a new 400a. 240v. 4 wire red leg delta service consisting of 2-200a. 3ph meters & MBs, all mounted on the building exterior.
As one tenant only required single phase for an existing 100a. panel I ran a 3 wire, single phase, 100a. 120/240 feeder from the main breaker load side, about 30' along the exterior wall surface to a 100 amp disconnect mounted immediately upon entry.
Conduit is 1" emt, all fitting are raintite, wire is #3 thhn.
I got a violation for this, without explanation, other than the #3s weren't properly protected on the 200a. MB.
Does the tap rule not apply here? I cited 240.21(b)(5) to the inspector to no avail.
He did seem confused though and said he would investigate further.
Any comments?
Much obliged.
As one tenant only required single phase for an existing 100a. panel I ran a 3 wire, single phase, 100a. 120/240 feeder from the main breaker load side, about 30' along the exterior wall surface to a 100 amp disconnect mounted immediately upon entry.
Conduit is 1" emt, all fitting are raintite, wire is #3 thhn.
I got a violation for this, without explanation, other than the #3s weren't properly protected on the 200a. MB.
Does the tap rule not apply here? I cited 240.21(b)(5) to the inspector to no avail.
He did seem confused though and said he would investigate further.
Any comments?
Much obliged.