I installed a temporary pole service with a 100 amp meter socket and a small 100 amp panel with main lugs and spaces for 6 breakers, I used only 4 of the spaces for GFCI recpts for a new home constructions site, the inspector said that I needed to have a main breaker for the panel, I through you didn't need a main with less than 6 switches. Is the inspector right or wrong?
Steve
I installed a temporary pole service with a 100 amp meter socket and a small 100 amp panel with main lugs and spaces for 6 breakers, I used only 4 of the spaces for GFCI recpts for a new home constructions site, the inspector said that I needed to have a main breaker for the panel, I through you didn't need a main with less than 6 switches. Is the inspector right or wrong?