Rbalex... the fault-duty problem had been under discussion for quite a long time in the '60s, within the compay I was with at the time. With plants all over the word fitted with multiple Secondary-Selective and Spot-Network distribution systems the eventual conclusion was, as follows:
While possible, the situation involving coincident closure of say 'B' breaker and a 3-phase fault occuring in the secondary-bus or output circuits fed from the bus, was highly improbable, using what today is called, Probabilistic Risk Analysis, or PRA!
Regards, Phil Corso