G.E.Sparky
Member
- Location
- New York
Just ran URD 350 mcm wire with 4/0 neutral in sched. 40 to residential service.  Its a 200 amp underground service 500 feet long through a swamp.  I megged it with my meter at 1000v and got a reading of 114 megaohms phase to phase.  97 meg phase to neutral. Then 27 meg other phase to neutral.  should I be worried.  The conditions were very wet and it was raining. When pulling through --mud came through with wire but none of jacket looked even a bit scratched and it pulled really easy through the 4" sched. 40.  What do you guys think?
	
		
			
		
		
	
				
			 
				
 
 
		 
 
		 
 
		 
 
		