On a agricultural well and pivot service does the NEC state that inspection is required after the service disconnect is installed and wired?
On a agricultural well and pivot service does the NEC state that inspection is required after the service disconnect is installed and wired?
Maybe I didn't phrase the question correctly, the local power company requires a non fused disconnect before the meterbase and a fusible disconnect after the meterbase. The local inspector said that the NEC requires that all equipment be connected to the fusible disconnect before power can be applied to the service is he correct in this statement or, once the service is built and wired to the line side of the fusible disconnect should this be considered a complete service and power applied?
The inspector is probably within his authority by wanting to see all connections before signing off on the project.
Yes, but why not separate inspections, one for the service, and one for the equipment.