Client is asking to convert 4000A non-seg bus from transformer to swgr with cable. Due to the number of cables in parallel, we think there is going to be a connection issue. We contacted the switchgear manufacturer and are not getting good response. Client wants to move forward with the project and leave the manufacturer out of it, but we say we cannot sign/seal drawings without their input because we are not manufacturer's and don't want to be responsible for the modifications.
Questions: Would Contractors be willing to make bus modifications without manufacturers input; client seems to think that's what they did on another project. What about signing and sealing?