Hello,
I need to move my GEC and water pipe bonding for an ATS installation that will become the first disconnect. I thought it was against code to splice the GEC that connects the ground bar with the service entrance panel. However, I can't find this after reading through 250. I can't remember if I was just taught to run a new GEC (or move it) in a class as a best practice or if it's actually a hard requirement to avoid splicing.
Thanks
Bill
I need to move my GEC and water pipe bonding for an ATS installation that will become the first disconnect. I thought it was against code to splice the GEC that connects the ground bar with the service entrance panel. However, I can't find this after reading through 250. I can't remember if I was just taught to run a new GEC (or move it) in a class as a best practice or if it's actually a hard requirement to avoid splicing.