Ryan Campbell
Member
- Location
 - Denver, CO
 
I am doing a proposal for a six unit multi family dwelling with 6 200A interior panels located in each garage and a 125A outdoor house panel located on opposite end of building from outdoor meter bank.  I will have a fused disconnecting means at 600A protecting my feeders located with meter bank.  I am to run 2" PVC schedule 40 to each interior panel.  Do I need to encase my feeders in concrete if I route conduits under garage slabs to each panel? Also do I need to add a disconnecting means when exiting opposite end to feed my house panel?  I have read posts that tell me I have to have disconnecting means closest to point of entry so if I run conduits outside of building I would need a discon at every point of entry even if I am protected with my fused disconnect next to meter bank?
	
		
			
		
		
	
				
			
				