Hi folks,
Hoping for some clarity on this one. We have a situation with a 300-amp 3-gang meter bay at a power pole that provides 100-amp service underground to 3 isolated structures. Each meter is breakered.
Is there any issue connecting 3 different 20-amp pv systems to each of the structures with a backfeed at each service panel?
I seem to recall a need for a single point of connection.
Thoughts?