Here is the setup...a farm with 3 buildings...the Poco service comes into building one...here it feeds building 1 and has a disconnect for building 2...building 2 in turn feeds a panel in building 3.
Building 1 is a storage building, existing for unknown amount of time. The water is from a well.
Building 2 is a new storage barn/workshop....no rebar and no concrete floor.
Building 3 is an indoor riding arena...it's also new and has a sand floor...
How would you ground and bond these buildings...forget wiring sizing...just the physical act...
Building 1 is a storage building, existing for unknown amount of time. The water is from a well.
Building 2 is a new storage barn/workshop....no rebar and no concrete floor.
Building 3 is an indoor riding arena...it's also new and has a sand floor...
How would you ground and bond these buildings...forget wiring sizing...just the physical act...