A hospital consists of several interrconnected buildings seperated by fire and smoke walls. (You would have no way of knowing where one building starts and where one stops without looking at the plans).
It is fed by about 12 separate services, each from a different transformer and each to a different equipment room. There are also 3 generators in different locations that feed different buildings.
Problem: One building has its emergency generator load max'ed out. (208V).
Question; Can I run a 480V feeder from another building to supply loads in this building?
I think the general rule is one service per building, but this hospital is already criss-crossed with power from different sources.
It is fed by about 12 separate services, each from a different transformer and each to a different equipment room. There are also 3 generators in different locations that feed different buildings.
Problem: One building has its emergency generator load max'ed out. (208V).
Question; Can I run a 480V feeder from another building to supply loads in this building?
I think the general rule is one service per building, but this hospital is already criss-crossed with power from different sources.