john37
Senior Member
- Location
- Riverside, California
I have a question regarding multiple taps. Currently there is an existing 480-208/120V, 3 phase transformer that feeds an existing panel. Evidentially later on someone came in and tapped the panel bus to add another panel. We need to relocate the second panel that was tapped off the bus on the first panel but now the plans examiner made a comment that "Verify the transformer secondary conductor feeding Panel B, multiple taps from a single transformer secondary must originate at the transformer." I couldn't find in the NEC where it states this. Could someone please direct me to which Article that states this? Thanks.