Hi guys,
This is my first post so excuses upfront.
My question is as follows: NEC states that for the breaker selection of a PV system i cannot exceed the 120% from the busbar. That means that if the pullout specification of that panel says for example 125A Max and it has a 100 A Main Breaker installed, i have 50A of breaker available right??.
Thanks in advance.
This is my first post so excuses upfront.
My question is as follows: NEC states that for the breaker selection of a PV system i cannot exceed the 120% from the busbar. That means that if the pullout specification of that panel says for example 125A Max and it has a 100 A Main Breaker installed, i have 50A of breaker available right??.
Thanks in advance.