My understanding of 250.21(C) is that since 2005 you can no longer use the "next size up rule" for transformer secondary conductors. This means you need 1-600 mcm or 2-3/0 CU per phase on a 400A service and double that on an 800A service. However, a standard 400A cb has one lug per phase good for up to 500 MCM and a standard 800A cb has 2 lugs per phase good for up to 500 MCM. Do I have to order special lugs on a cb to meet the new requirement?
Am I missing an exception somewhere?