I am in the Army in a contingency environment. We are still bound by the NEC to ensure safety compliance. I am trying to verify my understanding of 230.82. Situation is this: Two structures are fed from a distro panel. The distro panel is fed by an MTS. The MTS has incoming commercial (750KVA xfrmr) on one side and a back-up generator on the other side. The question pertains to the commercially fed side. Does there need to be another means of disconnect between the xfrmr and the MTS. The person I am working with states that per 230.82 there should be another distro panel in that run. For some reason that does not make sense. Am I misreading something?
Thanx,
Mark
Thanx,
Mark