NEC 314.3 - Nonmetallic Boxes

Status
Not open for further replies.

Strathead

Senior Member
Location
Ocala, Florida, USA
Occupation
Electrician/Estimator/Project Manager/Superintendent
As I said in post #3, both the manufacturers and the NEC allow EMT. I have done GE, Mitsubishi,(open and closed now) Phillips, and Siemens units and all allowed EMT (ferrous materials).
We just did a GE last year. We had to use aluminum. It could have been the Electrical Engineer, not the manufacturer, but I don't know
 