A friend of mine lives in a rural area. He has to run from the POCO transformer about 1,000' to his house. The voltage at the pole is 600v. The design engineer says he needs to run 3 wires from the 600v transformer to the step-down transformer. Since this is a 1,000 run, the extra wire is a cost factor.
I don''t see the need for the third wire. Cant he run two 750kcm cables from the 600v transformer to the step-down transformer, then ground the tap at the load side and run it to the house?
I hope I'm being clear. I've been up for 20 hours and I'm can barely add and subtract right now
Any code references or other material to forward to the engineer would be appreciated.
Thanks
I don''t see the need for the third wire. Cant he run two 750kcm cables from the 600v transformer to the step-down transformer, then ground the tap at the load side and run it to the house?
I hope I'm being clear. I've been up for 20 hours and I'm can barely add and subtract right now
Any code references or other material to forward to the engineer would be appreciated.
Thanks