David Rogers
Member
- Location
- Lake County, California
I am on a project where there is a 120/208v, 3 ph feed from a building subpanel, 60 amps.  At this time, it is the only feed to a 100a, 120/208v, 3ph, load center (BR breakers).  Our project is to add a new 120/208v, 3 ph, generator, 3 pole transfer switch, and feed just this load center.  The load center feeds a freezer/frig at a school.  There is a bond conductor from the main service to the subpanel that feeds the load center,  and to the load center that has a #8.  Since the generator feed shares the neutral of the serving utility, I thought this was not a separately derived system, so a bonding conductor between the generator and the load center was all that was needed.  The design on the plans calls to add two ground rods and a #8 grounded bonding conductor from the ground bus of the load center to the new ground rods.  Is this correct?
	
		
			
		
		
	
				
			 
				
 
 
		