I got this as a pm from Camilo
hi,
just want to know what is meant by 3 cold and 2 hot starts for 11kV motors.
the sequence in the design specs stated like this: "three cold starts with respect to two hot starts shall be possible in sequence. It shall be interrupted between second cold start and the first hot start by a cooling period of maximum 30 minutes in case of motors for heavy start up conditions."
thanks in advance.
camilo