New Transformer Calcs

Status
Not open for further replies.

laketime

Senior Member
I am working on a project and things just went from no problem to "what???"...so I need some help. We are going to be feeding the building with 3 phase 480v to feed some new equipment. I am filling out a load sheet for the utility company and I need some 208v 3 phase loads included in this 480v service. I need to size a transformer that has a 480v primary and a 120/208v secondary. The 120/208v secondary will feed 4 machines with a start up of 150 amps at 3 phase 208. In addition they want some peripheral equipment fed with the machine. We are looking at 200amp 120v/208v feed per machine location. What would transformer size need to be?
 
The machines will be running concurrently. The peripheral equipment would be something small like a 120v 20 amp shrink wrap machine.
 