We are doing a job in which drop ceilings will be installed in a commercial building. Now I understand the code as saying that NM can not be used in OPEN RUNS. But above the drop ceiling are 2x12 trusses in which I was hoping to bore through and run the NM through with out violating code requirements. Has anyone done this and is it legel or should I stick to MC cable the whole way? By the way I was going to only use the NM for my feeder cables then branch off using a J box with MC cable to feed my lights.
Thanks!
Thanks!