Type DB-60 was submitted instead of EB-35 due to the fact it holds up better during the construction and installation process resulting is less wated and damaged ducts, however what is the difference between DB-60 and EB-35 I understand the wall thickness is different, the DB references NEMA TC 6, and the EB-35 NEMA TC 8? What is the difference these conduits are specified to be in a duct bank is it ok to put DB-60 in a concrete encased duct bank?. Everything I have seen indicates this ad direct burry where the EB states encasement burial? Also I noticed it is only rated for 90? wire installation what if you have primary cabling specified (rated) at 105?C what type of conduit is Required then? PVC 40 (I could not find the max. temp. for PCV sched 40 or 80) does anyone know where I can find this? In that installation than neither DB-60 or EB-35 would be acceptable? Than what would be? Just looking for some other opinions? Thanks. 