I have two 480V condensing units for a retail location that will be powered via a wireway and have a disconnect at the unit on the roof. My question is this, what are the code requirements for OCPD installation location coming out of the wireway? Can I install a fused disconnect at the unit only or do I have to have a OCPD device inside my space going up to the Condensing unit. If so , what does the NEC say about where I can install this OCPD?
Thanks
I have two 480V condensing units for a retail location that will be powered via a wireway and have a disconnect at the unit on the roof. My question is this, what are the code requirements for OCPD installation location coming out of the wireway? Can I install a fused disconnect at the unit only or do I have to have a OCPD device inside my space going up to the Condensing unit. If so , what does the NEC say about where I can install this OCPD?