Ozymandias
Member
- Location
- Missouri
Hello,
I am learning all I can about PV systems and want to design a system for the shop I work for. I am working towards the NABCEP installer certification but I need to get some systems under my belt. I have been searching the forum to find some answers but not having any luck so moderators please move or remove my thread if it is redundant.
The service from the pole is 208/120Y, this goes to an 400 amp service disconnect and 400 MDP. I am designing a 25 kw flat roof system and considering a supply connection. My original design was to have a single undersized inverter then entertained two SMA 10.3 kw inverters to manage the array but as I research the subject I wonder if I should have three SMA 7 kw inverters so that I can connect each inverter to two of the busbars of the three phase legs thus balancing the load. Or keep it at two inverters, each connected to two of the busbars of the three phases but not truly balanced across the phases. These inverter(s) will installed on the roof to satisfy rapid shutdown requirements and run into a PV service disconnect near the existing main disconnect. I hope I am making sense.
I am learning all I can about PV systems and want to design a system for the shop I work for. I am working towards the NABCEP installer certification but I need to get some systems under my belt. I have been searching the forum to find some answers but not having any luck so moderators please move or remove my thread if it is redundant.
The service from the pole is 208/120Y, this goes to an 400 amp service disconnect and 400 MDP. I am designing a 25 kw flat roof system and considering a supply connection. My original design was to have a single undersized inverter then entertained two SMA 10.3 kw inverters to manage the array but as I research the subject I wonder if I should have three SMA 7 kw inverters so that I can connect each inverter to two of the busbars of the three phase legs thus balancing the load. Or keep it at two inverters, each connected to two of the busbars of the three phases but not truly balanced across the phases. These inverter(s) will installed on the roof to satisfy rapid shutdown requirements and run into a PV service disconnect near the existing main disconnect. I hope I am making sense.