flatlander
Senior Member
- Location
- Diamond bar, CA , Tempe AZ
Hi all,
I was wondering if you electrical contractors out there are seeing abusive language in subcontracts from General Contractors or owners
I'm talking about where if you succeed in a change order you only get 10% above your actual cost, while the contractor gets 15 % overhead and on top of that 10 % profit.
Or contractor will not pay subcontractor for a change order unless paid by the owner first. Even if a signed change is agreed to
Or
At any time after execution of the contract the owner or contractor can require a 100% performance bond at the cost of the subcontractor.
If the owner escalates the time schedule the subcontractor will provide extra workers or overtime without extra charge.
Stuff like this.
I was wondering if you electrical contractors out there are seeing abusive language in subcontracts from General Contractors or owners
I'm talking about where if you succeed in a change order you only get 10% above your actual cost, while the contractor gets 15 % overhead and on top of that 10 % profit.
Or contractor will not pay subcontractor for a change order unless paid by the owner first. Even if a signed change is agreed to
Or
At any time after execution of the contract the owner or contractor can require a 100% performance bond at the cost of the subcontractor.
If the owner escalates the time schedule the subcontractor will provide extra workers or overtime without extra charge.
Stuff like this.