Don't do a lot of underground work. This explanation may be too simplistic but wondering if you thought of time required for this install makes sense. Just want to make sure I'm not way off base. Thank you.
Scope. Area is 70'x70'. Most all work is underground with PVC schedule 40 and RGS elbows and XHHW wire.
All work fed from NEMA 3R panel
All work is 3/4" conduit except control panel feeds.
All excavation, backfill and restoration by others.
Mounting of control panels by others.
1. Install 600A panel and supports.
2. Run a feed to each auger control panel about 30' each - 2" w/ 3 #3/0 and 1 #6
3. Install (3) duplexes on low wall and (1) in storage container.
4. Install and feed Misc 20A loads in storage containers. Mostly roll up doors with push button.
5. Install and feed (4) 15' light poles(aluminum). Not bases. Also ground rod at each.
6. Install (3) 8' surface fixtures in storage containers with switching.
I come up with about (2) men 12 days. This is for 7 hour days. Looking at it I think this is very much on the high side.

Scope. Area is 70'x70'. Most all work is underground with PVC schedule 40 and RGS elbows and XHHW wire.
All work fed from NEMA 3R panel
All work is 3/4" conduit except control panel feeds.
All excavation, backfill and restoration by others.
Mounting of control panels by others.
1. Install 600A panel and supports.
2. Run a feed to each auger control panel about 30' each - 2" w/ 3 #3/0 and 1 #6
3. Install (3) duplexes on low wall and (1) in storage container.
4. Install and feed Misc 20A loads in storage containers. Mostly roll up doors with push button.
5. Install and feed (4) 15' light poles(aluminum). Not bases. Also ground rod at each.
6. Install (3) 8' surface fixtures in storage containers with switching.
I come up with about (2) men 12 days. This is for 7 hour days. Looking at it I think this is very much on the high side.