I went to Baldwin, Georgia city hall today to pull a permit. They are only accepting permit applications 2-3:00, Tues & Thurs, must make appointment ahead of time, 4 appointments per hour (8 permits per week). This includes all construction, not just electrical. So I have to wait now until Tuesday 2:45 to start work.
Sounds like an entrapment scam to fine people for not getting permits. Sure does not help economy, people want to spend money and create jobs, and stimulate the economy then some government agency puts a halt to everything by limiting to only 8 permits per week. If you want to do things legally you need to plan a project and get on the waiting list possibly years in advance. Then along comes code changes and plans need revised by the time project actually gets the OK to start.:thumbsdown: