ElectricianJeff
Senior Member
- Location
- Southern Illinois
Next week I am upgrading a home from 60 to 200 amp. I am relocating the breaker panel from the basement to the garage. My plan is to extend all the branch circuits, about 25 or so, out of the basement up an inside wall of the garage sleeved in 2" PVC, pop across the garage attic and then down into the service panel.
My plan is to combine as many of the 120V circuits into MWBC's to reduce the number of romex wires I will need to pull. Is there any problems, code or otherwise, to do it in this fashion? Basically I would be running about 6 12/3's from my service panel to my junction box in the basement and then splitting each one out to 2 12/2's. I would be putting these circuits on 2 pole breakers even though we are not on the '08 code. I have done this in new construction many times. Does it make a difference because these are existing circuits? Also, I suspect but haven't checked yet that some of the older circuits are 2 wire with no EGC. Does this fact affect my plan.
I'm second guessing myself on this for some reason.
My plan is to combine as many of the 120V circuits into MWBC's to reduce the number of romex wires I will need to pull. Is there any problems, code or otherwise, to do it in this fashion? Basically I would be running about 6 12/3's from my service panel to my junction box in the basement and then splitting each one out to 2 12/2's. I would be putting these circuits on 2 pole breakers even though we are not on the '08 code. I have done this in new construction many times. Does it make a difference because these are existing circuits? Also, I suspect but haven't checked yet that some of the older circuits are 2 wire with no EGC. Does this fact affect my plan.
I'm second guessing myself on this for some reason.