I wasn't suggesting that it'd be a good design decision, though I did not embellish to that degree. Mostly just pointing out that splicing is permitted in cable tray.Splice in a new installation? Not in our plants........Not unless it is a MV and complex run that just simply can not be done in a single pull. Avoid it like the plague......
Aside from pointing out the derating issue in my other post, there would still be a question as to whether the contractor is obligated to provide unspliced conductors.