Impac
Member
- Location
- Philadelphia
I have a 400amp 3ph service that I am doing and it calls for 700al now I have paralleled it own to 4/0al @132ft. The inspector at first said that could not run all of the phases in one 4inch conduit. I quickly won that argument. But then he came back to me with my derating factor. Now after I did my calculations i came up with .06 and the inspector came up with .083. Can someone tell me if this is correct because I have been thrown for a loop here and I am either going to have to pull all this wire out and redo the entire service or leave it put. Someone out there please respond thank you in advance.